Hi,
For some reason, every task I have ever worked on is now showing as not complete and they have all re-appeared.
Additionally, when I have a header task, I can no longer keep it open - even if I set 'none' to completion.
Example;
HEADER TASK (NONE COMPLETION)
TASK A
TASK B
TASK C
When I 100% task A, B and C there appears no way to keep the header task open as it now automatically sets to 100%
We end up with this
HEADER TASK (100%)
TASK A (100%)
TASK B (100%)
TASK C (100%)
What I actually want;
HEADER TASK (NONE)
TASK A (100%)
TASK B (100%)
TASK C (100%)
Tasks Issues
Moderators: TerryRogers, Max
-
- Site Admin
- Posts: 16640
- Joined: Thu Nov 25, 2004 3:12 am
- Has thanked: 1552 times
- Been thanked: 1064 times
Re: Tasks Issues
Could you walk us through the steps to reproduce the issue? That would really help!For some reason, every task I have ever worked on is now showing as not complete and they have all re-appeared.
Regarding your second question, please make sure to disable the option labeled "Automatically calculate parent task progress based on child tasks." You can find this option by navigating to Tools -> Options -> Modules -> Tasks.
Android version of EssentialPIM. Keep all your data in sync!
-
- Expert
- Posts: 93
- Joined: Mon Jul 10, 2006 12:07 pm
- Has thanked: 8 times
- Been thanked: 7 times
Re: Tasks Issues
Hi,
Setting that option again helped fix the tasks being closed issue.
Not sure what reset it?
As to the tasks appearing, I didn't actually do anything. One day just the ones I was working on were visible. Next time I opened EPIM, all of them were visible?
No idea what happened?
I've closed them all and then just re-opened the open ones..
Cheers!
Setting that option again helped fix the tasks being closed issue.
Not sure what reset it?
As to the tasks appearing, I didn't actually do anything. One day just the ones I was working on were visible. Next time I opened EPIM, all of them were visible?
No idea what happened?
I've closed them all and then just re-opened the open ones..
Cheers!