Post by XineBBSA »

Hi,

For some reason, every task I have ever worked on is now showing as not complete and they have all re-appeared.

Additionally, when I have a header task, I can no longer keep it open - even if I set 'none' to completion.

Example;

HEADER TASK (NONE COMPLETION)
TASK A
TASK B
TASK C


When I 100% task A, B and C there appears no way to keep the header task open as it now automatically sets to 100%

We end up with this

HEADER TASK (100%)
TASK A (100%)
TASK B (100%)
TASK C (100%)


What I actually want;

HEADER TASK (NONE)
TASK A (100%)
TASK B (100%)
TASK C (100%)
admin
Site Admin
Posts: 16640
Joined: Thu Nov 25, 2004 3:12 am
Has thanked: 1552 times
Been thanked: 1064 times

Re: Tasks Issues

Post by admin »

For some reason, every task I have ever worked on is now showing as not complete and they have all re-appeared.
Could you walk us through the steps to reproduce the issue? That would really help!

Regarding your second question, please make sure to disable the option labeled "Automatically calculate parent task progress based on child tasks." You can find this option by navigating to Tools -> Options -> Modules -> Tasks.
Android version of EssentialPIM. Keep all your data in sync!
XineBBSA
Expert
Posts: 93
Joined: Mon Jul 10, 2006 12:07 pm
Has thanked: 8 times
Been thanked: 7 times

Re: Tasks Issues

Post by XineBBSA »

Hi,

Setting that option again helped fix the tasks being closed issue.

Not sure what reset it?


As to the tasks appearing, I didn't actually do anything. One day just the ones I was working on were visible. Next time I opened EPIM, all of them were visible?

No idea what happened?

I've closed them all and then just re-opened the open ones..


Cheers!
Post Reply