In EPIM v11.2.5, displaying the duration of tasks is not correct when their duration equals 24 hours. In the screenshot, the status bar shows a duration of 0 minutes when I would expect to see either 24 hours or 1 day.
Regards,
DG
Tasks: Duration display is wrong when tasks total 24 hours
Moderators: TerryRogers, Max
-
- Site Admin
- Posts: 15650
- Joined: Thu Nov 25, 2004 3:12 am
- Has thanked: 1419 times
- Been thanked: 986 times
Re: Tasks: Duration display is wrong when tasks total 24 hours
Unable to reproduce. Please check if the same happens with the new DB. If so, forward us that file. Thanks!